An Opportunity Zone construction loan is an ordinary construction loan on a project that also has to satisfy OZ tax tests. As of October 2026, lenders underwrite these deals like any other construction deal. The OZ-specific work is making the draw schedule finish inside the 30-month substantial improvement window and the 31-month working capital schedule.
How a construction loan is structured
A construction loan funds in draws as work is completed, rather than in one advance. Lenders commonly require the borrower's equity to go in first or alongside the loan, inspect work before releasing each draw, and look for a permanent loan or sale to repay the construction loan at completion. Exact terms vary by lender and are set in the term sheet; this site does not publish rates or loan-sizing figures.
What a lender evaluates: sponsor experience and liquidity, the hard and soft cost budget and contingency, the general contractor and contract, plans and permits, the appraisal and market study, and the exit. OZ status does not stand in for any of these.
Two paths to qualifying property: original use or improvement
Opportunity Zone business property must be bought from an unrelated party, and either its original use in the zone must start with the fund or business, or the fund or business must substantially improve it (IRC 1400Z-2(d)(2)(D)(i)). Which path applies changes what the construction loan has to accomplish.
| Project | OZ path | What the budget has to do |
|---|---|---|
| Ground-up building on bought land | Original use of the new building | Original use begins when the building is first placed in service in the zone (26 CFR 1.1400Z2(d)-2(b)(3)(i)(A)). Land generally does not need improving. |
| Rehab of an occupied existing building | Substantial improvement | Add more than the building's adjusted basis within any 30-month period after purchase (more than 50 percent in an entirely rural zone). |
| Rehab of a long-vacant building | Possibly original use | Real property vacant for the periods set in 26 CFR 1.1400Z2(d)-2(b)(3)(i)(B) and still vacant at purchase can qualify as original use. See original use and vacant property. |
Worked example: sizing the improvement budget
Hypothetical example
Suppose a fund's business buys an existing building for $3,000,000, and the purchase price is allocated $1,000,000 to land and $2,000,000 to the building. The land does not need to be improved, so the test runs on the building's $2,000,000 basis.
- Standard zone: additions to the building's basis must exceed $2,000,000 within a 30-month period after purchase.
- Zone made up entirely of rural area: additions must exceed 50 percent of basis, so more than $1,000,000. This 50 percent threshold applies to determinations made on or after July 4, 2025 (Notice 2025-50, section 5).
If the business closes on the building on March 1, 2027 and the draw schedule puts the last major draw in month 34, the schedule does not show the test being met within months 1 to 30. The sponsor would need to move spending earlier, or confirm with a tax adviser which 30-month period is being measured.
Matching the draw schedule to the OZ schedules
Three schedules have to agree: the lender's draw schedule, the substantial improvement window, and the business's written working capital schedule.
- Start with the purchase date. The 30-month improvement period runs after acquisition. Count forward and mark month 30.
- Write the working capital plan to match. The written designation can cover "the acquisition, construction, and/or substantial improvement of tangible property" in the zone, and the money must be spent within 31 months of receipt (26 CFR 1.1400Z2(d)-1(d)(3)(v)(A)–(B), read October 30, 2026).
- Use the 62-month option only if it fits. A start-up can chain 31-month applications for up to 62 months, but each must independently meet the rules and later infusions must be part of the original plan (26 CFR 1.1400Z2(d)-1(d)(3)(vi)(A)).
- Know which delays are excused. Waiting on government action on a completed application does not break the working capital schedule (26 CFR 1.1400Z2(d)-1(d)(3)(v)(C)). A federally declared disaster can add up to 24 months. Lender and contractor delays are not on that list.
- Put the dates in the loan documents' timeline. A completion date in the loan agreement that sits past the OZ deadlines is a mismatch worth fixing before closing, not after.
OZ questions a construction lender may ask
- When does the QOF equity fund, and is any of it conditioned on investors' 180-day windows?
- Which entity owns the property and borrows: the fund, or a qualified opportunity zone business it owns?
- If the project is in a 2018 zone, was the property bought before 2027, or does a transition rule apply?
- What happens to the sponsor's equity plan if the fund fails a semiannual test or a cure period?
What to send
A complete package usually includes the sources and uses, the construction budget and draw schedule, the general contractor contract or bids, plans and permit status, the purchase contract with the land and building allocation, sponsor financials, and the OZ test schedule described above. Send it through the financing form or to desk@janover.co. Janover Capital LLC arranges loans; it is not a lender, a fund sponsor or a broker-dealer, and it usually responds within one business day.
Common questions
Can you get a construction loan for an Opportunity Zone project?
Yes. OZ projects use ordinary construction loans from banks, debt funds and other lenders. The lender underwrites the sponsor, budget, plans, market and exit as it would for any project. OZ status does not change those requirements.
Does construction loan money count toward substantial improvement?
The substantial improvement test looks at additions to the building's basis within a 30-month period, not at the source of the cash. Capitalized construction costs funded by a loan add to basis like costs funded by equity. Ask the project's tax adviser how specific costs are treated.
Does new construction have to meet the substantial improvement test?
Generally not in the same way. Property whose original use in the zone begins with the fund or business qualifies through original use. Substantial improvement applies to existing property bought for the project. Land generally does not need to be improved.
What happens if construction runs past 31 months?
The working capital safe harbor requires the business's working capital to be spent within 31 months on a written schedule, extendable to 62 months for start-ups through a qualifying second application. Delay waiting on a completed government application does not break the schedule; a slow loan or contractor delay is not excused by that rule.